Monday, 3 August 2015

Week 15: Fireplace design and distracting ourselves (3-7 Aug)

Week 15: Distracting ourselves by choosing a fireplace (3-7 August)
 


The fire:
  • We want the widest possible fire – maybe the Regency Gem fire 54 (see below)
  • Want to ensure it is effective heating open plan area not just decorative
  • Want to get a traditional log fire media (look like a wood fire, see the second picture below) Gemfire 54 gas fireplace
  • HZ54 F 1872x1040

Design:
  • Closest designs to what we liked are image 1 and 2 below. 
  •  Want to fit TV above the fire but not too high, so this may mean we mount the fire very low to the floor and that any sort of bench top needs to go above the fireplace (see image 1).
  • We want some sort of cabinet to hide the DVD player etc, ideally with the ability to use the remote through the door or another mechanism (see image 4).
  • Want a stone feature wall as a backdrop to the fire, example of the Coolum below (image 7).
  • Want to minimise the metal surrounding the fire to the narrowest possible, likely stainless steel, with stone cladding coming up to the edges (see image 1/2/5/6)

IMAGE 1: Could do fire mounted directly on ground and benchtop above like this, so it creates a wide bench across both voids (DVD player etc on the bottom section of voids). Would still want the centre section to have some stone featuring. The bench top could be made of oak to match our flooring (engineered lime washed oak – we may be able to source from flooring supplier?)


IMAGE 2: Alternatively we could use the void spaces where they are say 70-80cm deep (void depth plus fireplace depth) could create sitting spaces.


IMAGE 3: Backlit niches with shelving, cupboards below would be translucent glass so remotes could pass through.

Like the stone background (and no recess around TV so doesn’t limit size of TV in future). Keep flat stone or recess the whole top half of the feature wall by the minimum recess required to the TV to be behind the fireplace…or add a small dividing shelf if required like in the above (as a last resort) This TV ends up too high in placement.


IMAGE 4: Example of translucent cupboards down low for DVD player etc. Our middle section would be wider and stone clad.


IMAGE 5: Don’t need a ledge sticking out like this one…
BUT….
IMAGE 6 AND 7:

If we need a feature where the fire is set on the ground then a thick stone base feature like this would be a nice option (would be unnecessary if have a benchtop like above)












STONE CLADDING

IMAGE 8: We like this stone cladding – this example is from EcoOutdoor Random Ashlar range in Coolum colour


https://www.ecooutdoor.com.au/products/natural-stone-walling/random-ashlar/coolum/

or a more green toned stone like on the right (image 9)

Week 13-14: The case of the disappearing bricklayers (20-31 July)

Week 13-14: Only Slug trails remain. The case of the disappearing bricklayers (20-31 July)
 
 Two weeks into bricklaying we thought things were going slowly... now they just are not going at all. Only slug trails remain as evidence of our bricklayers and from the start of week 11 (20/7) they just didn't show up. One small flicker of excitement was electricians installing a private pole for our telecoms.

 
 



 

 
Scaffolding was delivered on Friday 24/7 (was due for Wed delivery) and thankfully the scaffolding guys worked through their Saturday to get it erected and make up for lost time.

Delivered...
 Erected
 
To no avail sadly as week 12 the bricklayer only showed up one day... and then only because the site supervisor was meeting him there! That day bricks were distributed around all the scaffolding ready for laying... but no actual laying of bricks. The original plan was to expect 1-2 (week 11-12) weeks to brick downstairs, then they disappear for 1-2 days while the scaffolding goes up, then back or a couple of weeks for bricks upstairs (Week 13-14). Unfortunately, we are still at the stage of being bricked only to under window height (about a third of the job if that?).


At least the bricks were placed on scaffolding?
Bricks to the rear of the house (alfresco at left) still below windows.



Maybe they were just too cold to keep working? Apparently they were cold enough to light a bonfire on our site... with our bricks?! Hope they made a nice damper and billy tea or something so it was worth their while.

More bricks distributed around scaffolds on the low/east side of the house - in a tempt that maybe one day they will actually be laid!






It is hard to describe just how disappointing it is to turn into our street loaded with excitement and see zero progress and no sign of any trades. Our site supervisor is doing his best, he's now got the Construction Manager involved but the tradies just aren't showing up. He says he never gets this problem with his Central coast trades, seems to be a Sydney trades issue. I guess if they find a job closer to home or better paid they give it preference. We've offered to tip in extra cash incentives to get his usual coastal crew to travel to Sydney and get the job done faster.

We've found it especially sad to see no progress because we sold our townhouse at auction last weekend and will be renting elsewhere until the build is complete... and that end date feels further away than ever and we're feeling a bit homeless.


In one happy upside, we got a great price for our sale and we are celebrating by adding a fireplace to our living room in the open plan space to the rear of the house. Its something we have always dreamt of having as the heart of our house but just couldn't find the budget.

SO, to happier news, THE FIREPLACE in my next post.

And hopefully soon more news to report on bricklaying progress.